Hydro Testing Procedure for Purified Water Distribution Loop and Purified Water Storage Tank

  • Hydro Testing Procedure for Purified Water Distribution Loop

  • Objective : To ensure that the Purified Water Distribution Piping is Leakage proof from TC joints & Orbital Weld joints.
    Scope :Applicable for Hydro Testing of Purified Water Distribution Loop
  • Procedure :
  • Fill the Purified Water Distribution piping loop completely with Purified Water from the Supply line up to last end of Return line.
  • Close all the Sampling Valves & Zero Dead Leg Valves tightly.
  • Close the Last end point of Return line with TC Blind.
  • With the help of hand pump from supply line create a pressure of around 10 kg/cm2 and maintain it for 1 hour.
  • Observation should be filled in Hydro Test Report

 

  • Hydro Testing Procedure for  Purified Water Storage Tank
  • Objective : To ensure that the  Purified Water Storage Tank is Leakage proof.
    Scope :Applicable for Hydro Testing of  for  Purified Water Storage Tank
  • Procedure :
  • Fill the Purified Water Storage Tank completely with Water from the Purified Water Inlet nozzle.
  • Close all the Nozzles with TC Blinds.
  • With the help of hand pump from supply line create a pressure of around 4.5 kg/cm2 and maintain it for 1 hour.
  • Observation should be filled in Hydro Test Report

 

Pharma More Jobs and post Please click here

About Pharmaceutical Guidanace

Ms. Abha Maurya is the Author and founder of pharmaceutical guidance, he is a pharmaceutical Professional from India having more than 18 years of rich experience in pharmaceutical field. During his career, he work in quality assurance department with multinational company’s i.e Zydus Cadila Ltd, Unichem Laboratories Ltd, Indoco remedies Ltd, Panacea Biotec Ltd, Nectar life Science Ltd. During his experience, he face may regulatory Audit i.e. USFDA, MHRA, ANVISA, MCC, TGA, EU –GMP, WHO –Geneva, ISO 9001-2008 and many ROW Regularities Audit i.e.Uganda,Kenya, Tanzania, Zimbabwe. He is currently leading a regulatory pharmaceutical company as a head Quality. You can join him by Email, Facebook, Google+, Twitter and YouTube

Check Also

Alarm management & Alarm Challenge Test

Alarm management Alarm management is the understanding, design, implementation, and use of effective alarm capabilities …